***This project has been postponed and tentatively scheduled for 2025 see notices below.***
The City of Apple Valley 2022 Capital Improvement Program identifies potential street reconstruction, water and storm replacement and lining of the sanitary sewer on 142nd Street W from Cedar Avenue to Galaxie Avenue.
This project is tentatively scheduled for construction in 2023.
Contact the Apple Valley Engineering Department at 952-953-2427 or email tim.biberdorf@applevalleymn.gov for more information.
March 1, 2023
Dear Resident:
As you are aware, your neighborhood was scheduled to be a part of our 2023-104 Street Improvement Project. During the design process, City staff determined that the existing underground utilities are not up to current City standards. Because of the additional work needed and required funding, the project will be delayed in your area. Once The City of Apple Valley re-evaluates the Capital Improvement Plan (CIP), we will update you as to when the improvements are anticipated to be completed in your area.
If you have any questions, please email me, Tim Biberdorf, at tim.biberdorf@applevalleymn.gov or call me at (952) 953-2427.
CITY OF APPLE VALLEY
Public Works Department
Fall Neighborhood Meeting 11/16/22
Brandon S. Anderson, P.E.
City Engineer
Email (Not monitored 24 hrs.)
7100 147th St. W.
Apple Valley, MN 55124
Ph: (952) 953-2400
Fx: (952) 953-2515