157th St and Hayes Road Street Improvements (2023-107)

The City of Apple Valley 2023 Capital Improvement Program identifies a full depth Mill and Overlay and storm sewer improvements at the following locations:

  •  Hayes Road between 150th St W and 140th St W

A project kick-off meeting by the City Engineer is scheduled for residents on Hayes Road at 5:30 p.m. on May 18, 2023, at the Apple Valley Municipal Center, 7100 147th Street West, to provide more detailed information regarding the project. Project timelines and anticipated disruption of access to resident properties will also be discussed at this meeting.  

  • 157th St W between Cedar Avenue and Galaxie Avenue

 The project development tasks for the proposed improvements would involve the following scope of work. 

 

Conduct a topographical field survey to collect ground elevation, utility locations, and surface features within the proposed work zone.

 

Conduct a geotechnical investigation and soil borings within the work zone.

 

Conduct a neighborhood informational meeting to discuss the project with residents.

 

Prepare plans, specifications, and a project cost estimate and schedule for construction

 

MnDOT review of project plans. 

Review project plans and cost estimate with the City Council prior to bid process. 

Contact the Apple Valley Engineering Department at 952-953-2409 or email nate.becker@applevalleymn.gov for more information.

Contact Us

  1. Brandon S. Anderson, P.E.
    City Engineer
    Email (Not monitored 24 hrs.)

    7100 147th St. W.
    Apple Valley, MN  55124

    Ph: (952) 953-2400
    Fx: (952) 953-2515

    Hours


    Monday - Friday
    8:00 am - 4:30 pm

  1. Maps
  2. Notices
  3. Project Information